Worked example: PFMEA and control plan for a machined bracket
Guide · Examples · 9 min read
A concrete, end-to-end example — process flow, failure modes, S/O/D scoring, Action Priority and the matching control-plan lines.
Abstract method is easy to nod along to and hard to apply. So let's walk one small, concrete part all the way through — process flow, PFMEA, Action Priority and the matching control plan — using a machined and welded suspension bracket. It's deliberately small; a real analysis would have more rows, but the shape is exactly this.
The process flow
The bracket is made in five steps:
- Saw bar stock to length
- Mill the mating faces
- Drill & ream the Ø12 mounting bore (special characteristic — drives assembly alignment)
- MIG weld the gusset (special characteristic — load-bearing, safety)
- Powder coat
Two steps carry special characteristics: the bore position (significant — fit/function) and the weld penetration (critical — safety). Those are the rows we expect to drive the risk.
The PFMEA rows
For each step we name the failure mode, its effect and cause, then rate Severity, Occurrence and Detection and read the Action Priority:
| Step | Failure mode | Effect | S | O | D | AP |
|---|---|---|---|---|---|---|
| Saw | Length out of tolerance | Downstream rework | 4 | 4 | 4 | Low |
| Mill | Face flatness out of spec | Poor mating surface | 5 | 4 | 4 | Low |
| Drill & ream | Bore position out of tolerance | Bracket misaligns at assembly | 8 | 3 | 3 | High |
| MIG weld | Insufficient weld penetration | Joint fails under load (safety) | 9 | 2 | 4 | High |
| Powder coat | Coating thickness too low | Corrosion in the field | 6 | 7 | 5 | Medium |
Reading the risk
Notice what Action Priority does here. The weld is High even though it's expected to occur rarely (O2) — because Severity 9 (a safety effect) dominates. Under the old RPN it would have scored 9 × 2 × 4 = 72 and might have sat below a nuisance item; under AP it's correctly at the top of the list. The bore is also High (S8 with modest detection). The powder-coat row is Medium — frequent enough and hard enough to detect to deserve attention, but not safety-critical. The saw and mill rows are Low: real, but the team can address them at its discretion.
So the optimisation effort goes to two places: reduce occurrence on the weld (better fixturing, welder qualification, parameter monitoring) and improve detection/prevention on the bore (in-process gauging, a reamer-wear schedule).
The matching control plan
Every High and Medium row needs a controlling line in the control plan. For our two special characteristics:
| Characteristic | Spec | Method | Sample / freq. | Reaction plan |
|---|---|---|---|---|
| Bore position (SC) | Ø12 H7, position ⌀0.1 | CMM | 5 pcs / shift | Quarantine, adjust fixture, re-verify |
| Weld penetration (SC) | Per WPS, min. penetration | Macro-etch + visual | 1 / lot + 100% visual | Stop, re-qualify settings, contain lot |
| Coating thickness | 60–120 µm | Coating gauge | 3 pts / pc | Re-coat, adjust gun, re-measure |
The special-characteristic thread
This is the test of a coherent package: both special characteristics appear in the PFMEA (as the high-risk rows) and in the control plan (as controlled lines with reaction plans). If the weld were in the PFMEA but missing from the control plan, you'd have identified a safety risk with no production control for it — the classic orphan, and an instant audit finding. (See Special characteristics explained.)
In SolidLaunchpad this whole example is one connected model: the five steps are shared by the PFMEA and the control plan, the Action Priority is computed live, and the two special characteristics are single objects the method check watches across both documents. You can draft the first version of all of it from a paragraph describing the bracket — then refine the rows that matter.
See it live in SolidLaunchpad
Describe a part and get an AIAG-VDA PFMEA, control plan and the 18-element PPAP — connected, with the method checking itself.